Bidar House Construction | Construction progress and other updates (March 23rd, 2021)

First of all, thank you so much for the quick response.  Based on that response, I had given our commitment to support  by contributing Rs 1,00,000 /- (50k from our internal fund and 50k from our extended group). They started the work in the same week itself and it's progressing really fast. 





 



 

They also had shared a plan and estimate (Rs 1,79,000 /-)  with us before they started the work.  Before getting in to those details, I would like to share the current financial status and additional help they require. They are able to raise only 40K so far (excluding our contribution) and hence they are still short of  40k. When they mentioned they may have to compromise on the type of roofing and may not be able to plaster the whole house because of this, I said we will try and stretch a bit (1,40,000 /- instead of 1,00,000/-). That means we have to raise 90,000/- from our extended group and will need your help there.  Rs 36,000/- is what I have managed to raise so far from the extended group. 

 By the way, we have already transferred 55K till now.

                                                                Plan of the house



                                                                      Last sheet of the Estimate doc

             

                                                                     Expenses so far



 

 

  



 

 

No comments:

Post a Comment